Lee County, Alabama: what's coming.

We track what was proposed, what cleared, what stalled, and what got built in Auburn, Opelika, and Lee County. Every entry carries a source and the date we last checked it.

The read · October 2, 2026

What the pipeline adds up to.

Lee County had 85,379 housing units in July 2025.1 The Auburn and Opelika pipeline on this page holds about 14,000 more, counting planned developments at their approved maximum. That is 16 percent of everything standing today. The county issued 1,575 residential building permits in 2025.1 At that pace, the pipeline is about nine years of construction. Some of it will move faster. Some of it will never break ground. Approved is not built.

North Auburn gets a town center

The largest project on the list is The Foundry at North College, by Jolly Development. It sits north of Hickory Dickory Park and west of the Publix on East University Drive.3 The council approved the plan unanimously in March: about 282 acres, seven phases over 15 years, and up to 2,425 homes, including a maximum of 625 apartments and 1,800 houses and townhomes. The plan also carries 275,000 square feet of commercial space and 60,000 square feet of office.2 About 41 percent of the property is a greenway along Saugahatchee Creek, with trails and a flood buffer.3

Read the housing numbers as ceilings. A council amendment lowered the minimum number of units and the minimum unit size, so the developer has room to build less.4 Another amendment banned short-term rentals inside the development.3

The road comes first. Phase One builds a connector parallel to Shug Jordan Parkway, linking North College Street to North Donahue Drive with a central roundabout.2 The city and the developer split the roughly $8 million cost, and the developer pays its half when the road is done.3 How the project meets North College, a state route, is still being worked out with ALDOT.2

In context: The Foundry is about three-quarters of North Auburn's housing pipeline, and its apartment cap alone is larger than any single complex on this page. Plains High School is scheduled to open next door in fall 2028. Shug Jordan Commercial has filed 59 acres of mixed use nearby. A school, a connector road, and a retail center arriving together is how a suburb gets a town center. At 15 years, most of it is a 2030s story.

Students: 2028 is the year to circle

RISE Auburn (718 beds) and The Mark (825 beds) both target fall 2028. That is about 1,500 private beds. Auburn enrolled 6,112 first-year students in fall 2025, with total enrollment just over 35,000.5 The new beds equal about a quarter of one freshman class, or about 4 percent of the student body. The East Thach hall adds 680 campus beds but replaces Cambridge Hall, so its net gain is smaller.

The same window holds Plains High School's opening and the Jordan-Hare north end zone project, which runs through spring 2029. Four large projects on one calendar will compete for the same trades.

Opelika builds rooftops

Four Opelika subdivisions account for about 1,740 lots: Woodhaven (about 624), Bridgewater (541), Mayfair (401), and Crawford Reserve (171). Four apartment projects add 1,120 units, but only Springs at Opelika has started. Society Hill needed a 12-month extension in August. Approvals can sit.

The city is paying for roads to serve the new neighborhoods: $7.6 million in July contracts, including Bridgewater Boulevard and the Mill Village roundabout. Downtown, The Mill plans 327 homes over about ten years, and its first 183-lot plat was filed in September.

Jobs: announcements and payroll

The industrial projects on this page that state a job count add up to about 500 jobs: Faith Technologies (200+), Vulcaflex (130), GMB USA (75), Yongsan (about 68), Shinhwa (20), and Channing Street Copper (about 15). Metro manufacturing employment was 7,500 in June 2026, unchanged from a year earlier.6 The announced jobs would add about 7 percent.

The metro added 2,700 jobs over that year, reaching 83,600. Leisure and hospitality added 1,100 of them, about four in ten.6 Announced jobs arrive over years. Payroll counts arrive monthly. The factories are coming, and the hiring will show up later. But 500 jobs against 14,000 homes says the homes are not following the factories. The university and people moving in are driving housing here.

What we're watching

How we count: the pipeline includes filed, approved, and started projects in Auburn and Opelika. Planned developments count at their approved maximum. Project figures without a number here come from the list below, where each row carries its source. Percentages compare the pipeline with Census housing estimates and Alabama Department of Labor metro employment.

  1. U.S. Census Bureau, QuickFacts: Lee County, Alabama (housing units, July 1, 2025; building permits, 2025). Primary. Link · Checked October 2, 2026.
  2. Auburn Villager, Council approves plan for large, mixed-use development in north Auburn, March 5, 2026. Press, reporting meeting materials. Link · Checked October 2, 2026.
  3. Opelika Observer, Auburn council paves way for mixed-use development, March 3, 2026. Press. Link · Checked October 2, 2026.
  4. The Auburn Plainsman, Auburn City Council approves new development project, March 2026. Press. Link · Checked October 2, 2026.
  5. Auburn University, Auburn achieves historic gains in student retention, graduation, career placement, September 2025. Primary. Link · Checked October 2, 2026.
  6. Alabama Department of Labor, Nonagricultural wage and salary employment, Auburn-Opelika MSA, June 2026 (preliminary). Primary. Link · Checked October 2, 2026.

Current as of the verified dates shown

What's shaping the area.

The larger projects: 100 or more homes or apartments, major commercial and mixed-use sites, industrial investment of $10 million or 50 jobs, and public projects of $10 million or more, plus smaller ones that change a main corridor. Smaller projects appear in the monthly issues.

Where growth is going

Schematic map of Lee County, Alabama: main roads, growth areas shaded by what they are mostly adding, and the tracked projects as dots colored by type.

Shaded areas are tinted by what each area is mostly adding. Dots are the projects in the list below: filled when construction has started, solid ring when approved, dashed when only filed. Roads and shapes are simplified. The counts below are every residential project in our pipeline data, assigned to the nearest area. A dash means nothing counted yet, not zero.

Growth areaMostly addingHomes and townhomes in the pipelineApartment units in the pipeline
Southwest AuburnHomes8020
Technology Park WestIndustrial jobs––
Northwest AuburnHomes9480
North AuburnMixed use, schools, homes2,468655
Downtown Auburn and campusStudent beds, campus buildings367883
US 280, Pepperell and Tiger TownApartments, commercial, hospital1,377935
Downtown OpelikaInfill homes, public housing rebuild617252
North OpelikaHomes; industrial reuse1,4230
East OpelikaHomes1,1380
South OpelikaHomes, apartments1,593517

Homes and apartments (10)

ProjectSizeStatusLast changeSourceVerified
Perryman Hill Apartments
3655 Veterans Pkwy, Opelika
265 unitsApproved
Conditional use
Mar 2026Opelika PC minutes, March 24, 2026Sept 23, 2026
Tree Tops II
2908 Birmingham Hwy, Opelika
338 unitsApproved
Conditional use
Mar 2026Opelika PC minutes, March 24, 2026Sept 23, 2026
Bridgewater
Logan Dr, Opelika
541 lotsApproved
Preliminary plat. Council awarded $1.53M Bridgewater Boulevard contract July 7, 2026.
Jul 2026Opelika PC minutes, Oct 28, 2025
Opelika Observer, July 7, 2026
Sept 23, 2026
Woodhaven
Ridge Rd (Lee Road 390), Opelika
~624 lots on 304.5 acresApproved
PUD, Ordinance 027-25, Sept 16, 2025
Sep 2025Opelika Observer public notices, Sept 25, 2025Sept 23, 2026
Crawford Reserve
1300 block Crawford Rd, Opelika
~171 lots on 73.3 acresApproved
PUD, Ordinance 006-26, Feb 3, 2026
Feb 2026Opelika Observer public notices, Feb 9, 2026Sept 23, 2026
Mayfair
S Uniroyal Rd, Opelika
401 lots plannedApproved
Phases 1 and 2 preliminary plats (246 lots)
Jun 2026Opelika PC minutes, June 23, 2026Sept 23, 2026
Society Hill Apartments
2900 Society Hill Rd, Opelika
265 unitsApproved
Conditional use; 12-month extension approved Aug 25, 2026
Aug 2026Opelika PC minutes, Aug 25, 2026Sept 23, 2026
Springs at Opelika
Gateway Dr at Capps Dr, Opelika
252 unitsStarted
Groundbreaking announced
Aug 2026Opelika Observer, Aug 11, 2026Sept 23, 2026
The Mill (Pepperell Village)
1st and 2nd Aves at 24th St, Opelika
$125 million over ~10 years; 327 homes and townhomes; office, retail, food on ~41 acresApproved
PUD approved 2025; 183-lot plat filed Sept 22, 2026; city awarded $3.34M Mill Village roundabout contract July 7, 2026
Sep 2026The Bama Buzz, July 15, 2025
Opelika PC agenda, Sept 22, 2026
Sept 24, 2026
Ridgecrest redevelopment (Auburn Housing Authority)
945 N Donahue Dr, Auburn
$21 million; 106 units rebuilt as 176 (70 for seniors)Approved
Council approved city funding Feb 2026
Feb 2026Opelika Observer, Feb 23, 2026Sept 24, 2026

Student housing and campus (5)

ProjectSizeStatusLast changeSourceVerified
LeMans Square and Chateau apartments
560 N Gay St and 560 Perry St, Auburn
Redevelopment; Chateau 126 unitsApproved
Council approved conditional uses Aug 18, 2026
Aug 2026Opelika Observer, Sept 1, 2026
Auburn PC agenda, Aug 13, 2026
Sept 23, 2026
RISE Auburn
712 W Glenn Ave, Auburn
240 units, 718 beds; $87 million permitApproved
Building permit issued June 3, 2026; due before the 2028-29 school year
Jun 2026The Bama Buzz, June 8, 2026Sept 23, 2026
The Mark
141 Wright St, Auburn
329 units, 825 bedsStarted
Under construction; delivery expected fall 2028
Mar 2026The Bama Buzz, March 16, 2026Sept 23, 2026
East Thach residence hall (Auburn University)
E Thach Ave at S Gay St, Auburn
680 beds; replaces Cambridge HallApproved
Trustees approved Nov 2025; demolition and construction planned for 2026
Nov 2025Auburn University, Nov 18, 2025Sept 24, 2026
Jordan-Hare north end zone events center
Auburn University campus
~300,000 SF, seven stories; events, dining, premium game-day spaceApproved
Final trustee approval April 17, 2026; construction planned summer 2026 to spring 2029
Apr 2026Auburn University, April 2026Sept 24, 2026

Commercial and mixed-use (6)

ProjectSizeStatusLast changeSourceVerified
Perryman Hill Plaza
US 280 at Veterans Pkwy, Opelika
65,000 SF center; 9-lot platFiled
Plat back before the planning commission. Grocery anchor unconfirmed.
May 2026Opelika PC agenda, May 26, 2026Sept 23, 2026
Birmingham Hwy rezoning
3400 block, Opelika
18.34 acres, R-4 to C-2 (gateway corridor overlay)Approved
Council adopted Ordinance 022-26, July 7, 2026
Jul 2026Opelika council minutes, July 7, 2026
Opelika Observer, July 7, 2026
Sept 23, 2026
Extreme Powersports dealership
4800 Birmingham Hwy, Opelika
$9.2 million permitApproved
Building permit issued May 22, 2026
May 2026The Bama Buzz, May 26, 2026Sept 23, 2026
The Foundry at North College
N College St at Shug Jordan Pkwy, Auburn
282 acres; up to 2,425 homes (up to 625 apartments and 1,800 houses and townhomes); 275,000 SF commercial and 60,000 SF office; seven phases over 15 yearsApproved
Jolly Development. Council unanimously approved annexation, PUD zoning, the development plan and an infrastructure agreement March 3, 2026. Unit counts are maximums. Plains High School is planned next door.
Mar 2026Auburn Villager, March 5, 2026
Opelika Observer, March 3, 2026
The Auburn Plainsman, March 2026
Oct 2, 2026
Farmville mixed-use development
E Farmville Rd at US 280, Auburn
Mixed-use PDD (size not yet published)Filed
Rezoning and conditional use on July 9, 2026 agenda; council approved a Farmville mixed-use amendment Aug 18
Aug 2026Auburn PC agenda, July 9, 2026
Opelika Observer, Aug 18, 2026
Sept 24, 2026
Shug Jordan Commercial
Shug Jordan Pkwy at N Donahue Dr, Auburn
58.92-acre PDD; mixed useFiled
Annexation, rezoning and conditional use on April 9, 2026 agenda. Same area as The Foundry.
Apr 2026Auburn PC agenda, April 9, 2026Sept 24, 2026

Industrial and data centers (5)

ProjectSizeStatusLast changeSourceVerified
Faith Technologies
Former Joann Fabrics distribution center, Opelika
$79 million; 200+ jobsApproved
Incentives. Start of work not confirmed.
Jul 2026WTVM, Feb 25, 2026Sept 23, 2026
Vulcaflex
3111 Haygood Ct, Auburn Technology Park West
~$70 million; 130 jobs; ~304,000 SF first phaseApproved
Council approved industrial conditional use Aug 18, 2026; site preparation reported
Aug 2026Opelika Observer, Aug 18, 2026Sept 23, 2026
Auburn Technology Park West expansions, 2026
Riley St, Haygood Ct, Biltmore Ln, Auburn
Shinhwa $37M, 20 jobs; 2A USA $32M; Duck Il ~$21M; Kamtec $9.2M; DIA, INFAC, Vertex permits; Seohan Plant #3 and KettenWulf requestsApproved
Mix of state announcements, city conditional uses and building permits
Aug 2026Made in Alabama: 2A USA, Aug 2026
Made in Alabama: Shinhwa, March 2026
Opelika Observer, March 3, 2026 (Shinhwa abatement, 20 jobs)
The Bama Buzz, July 6, 2026
Oct 2, 2026
Core Scientific data center expansion
Samford Ave, Auburn
$55 million permit; staff from 11 to 20+Approved
Building permit issued early 2026
Feb 2026WTVM, Feb 25, 2026Sept 24, 2026
Opelika industrial incentives, 2026
Orr Industrial Park and others, Opelika
GMB USA $9M, 75 jobs; Yongsan $4.46M, ~68 jobs; BS Logistics $1.2M; Channing Street Copper ~$1M, ~15 jobsApproved
Council tax abatements and state announcements, April to July 2026
Jul 2026Opelika Observer, July 7, 2026
Made in Alabama: GMB USA, April 2026
Sept 24, 2026

Schools, hospital, and public works (3)

ProjectSizeStatusLast changeSourceVerified
Plains High School and new junior high (Auburn City Schools)
North Auburn, beside The Foundry
$241.8 million in warrants for schools and facilitiesApproved
Council approved Aug 4, 2026; high school expected to open fall 2028
Aug 2026Opelika Observer, Aug 11, 2026Sept 24, 2026
East Alabama Health expansion
East Alabama Medical Center, Opelika
$76 million; critical care (30 ICU beds) and mental healthStarted
Under construction
2025WRBLSept 24, 2026
Opelika road contracts tied to new neighborhoods
Bridgewater Blvd; Hi-Pack Dr; Mill Village roundabout
$7.6 millionApproved
Council awarded contracts July 7, 2026
Jul 2026Opelika Observer, July 7, 2026Sept 24, 2026

This table is kept current between issues. Each issue keeps its own dated copy; corrections are noted on the issue.

Issues

How this is put together

Sources: Opelika Planning Commission and City Council; Auburn Planning Commission and City Council; the Opelika Industrial Development Authority; Lee County Commission (from later issues). Agendas and minutes are the primary record; press coverage fills in announcements and groundbreakings. We report what the record says and label what is not yet confirmed. Issues are dated and are not rewritten after they publish. Corrections are noted on the issue and carried into the next one.

See something we missed or got wrong? Tell us. How Redchip researches and verifies: Method.

Disclosure: the author is a partner in Vanguard Industrial Partners, which develops projects in this market and may have interests in or near properties listed here. General information only; see the disclaimer.