Lee County, Alabama

Updated November 6, 2026

Preliminary update, November 6. Opelika's permit and planning records are now read in full for November 2024 through November 6, 2026 (8,204 permits issued or applied for, 891 planning cases). Auburn's public permit map lists open permits only, so closed Auburn permits from earlier months are missing; Lee County and Smiths Station records have not yet been obtained. A passed final building inspection is not treated as a certificate of occupancy. The pipeline total and percentages in the read below carry over from earlier in the month and have not been recomputed.

Purple dots mark park and land context, separately filtered from projects. Project dots are filled when construction has started, solid ring when approved, dashed when only filed. Tracts large enough to see are shown as a shaded circle of their stated acreage, centered on the project; it shows size, not the property line. Dots placed from a street address say so; the rest are placed at the named road, intersection or campus and are approximate. Click a dot or a project for its status and source. The table below assigns every residential project in our pipeline data to its nearest growth area.

October 2026

What the pipeline adds up to.

Lee County had 85,379 housing units in July 2025.1 The Auburn and Opelika pipeline on this page holds about 14,000 more, counting planned developments at their approved maximum. That is 16 percent of everything standing today. The county issued 1,575 residential building permits in 2025.1 At that pace, the pipeline is about nine years of construction. Some of it will move faster. Some of it will never break ground. Approved is not built. This total has not yet been recomputed for the projects added on October 26.

North Auburn gets a town center

The largest project on the list is The Foundry at North College, by Jolly Development. It sits north of Hickory Dickory Park and west of the Publix on East University Drive.3 The council approved the plan unanimously in March: about 282 acres, seven phases over 15 years, and up to 2,425 homes, including a maximum of 625 apartments and 1,800 houses and townhomes. The plan also carries 275,000 square feet of commercial space and 60,000 square feet of office.2 About 41 percent of the property is a greenway along Saugahatchee Creek, with trails and a flood buffer.3

Read the housing numbers as ceilings. A council amendment lowered the minimum number of units and the minimum unit size, so the developer has room to build less.4 Another amendment banned short-term rentals inside the development.3

The road comes first. Phase One builds a connector parallel to Shug Jordan Parkway, linking North College Street to North Donahue Drive with a central roundabout.2 The city and the developer split the roughly $8 million cost, and the developer pays its half when the road is done.3 How the project meets North College, a state route, is still being worked out with ALDOT.2

In context: The Foundry is about three-quarters of North Auburn's housing pipeline, and its apartment cap alone is larger than any single complex on this page. Plains High School is scheduled to open next door in fall 2028. Shug Jordan Commercial has filed 59 acres of mixed use nearby. A school, a connector road, and a retail center arriving together is how a suburb gets a town center. At 15 years, most of it is a 2030s story.

Students: 2028 is the year to circle

RISE Auburn (718 beds) and The Mark (825 beds) both target fall 2028. That is about 1,500 private beds. Auburn enrolled 6,112 first-year students in fall 2025, with total enrollment just over 35,000.5 The new beds equal about a quarter of one freshman class, or about 4 percent of the student body. The East Thach hall, now under way, adds 680 to 696 campus beds by March 2028 (university sources differ), but it replaces Cambridge Hall, so its net gain is smaller.10 Concourse Hall's 371 beds already opened this summer.11

Off campus, Interlude Cottages on North Dean Road is building 235 to 243 rental cottages and duplexes, with a construction loan closed in March and completion targeted for 2027.13 Rental cottages compete with student apartments for the same upperclassmen and young households.

The same window holds Plains High School's opening and the Jordan-Hare north end zone project, which runs through spring 2029. Four large projects on one calendar will compete for the same trades.

Opelika builds rooftops

Four Opelika subdivisions account for about 1,740 lots: Woodhaven (about 624), Bridgewater (541), Mayfair (401), and Crawford Reserve (171). Four apartment projects add 1,120 units, but only Springs at Opelika has started. Society Hill needed a 12-month extension in August. Approvals can sit.

The city is paying for roads to serve the new neighborhoods: $7.6 million in July contracts, including Bridgewater Boulevard and the Mill Village roundabout. Downtown, The Mill plans 327 homes over about ten years, and its first 183-lot plat was filed in September.

Industrial sites and capacity: Opelika's technology park

A ready site is part of the development picture even before a tenant files a building plan. The City of Opelika and its Industrial Development Authority announced the approximately 105-acre Opelika Innovation and Technology Park in January 2020, along US Highway 280 West between Veterans and Waverly Parkways, in a designated Opportunity Zone.15 The city's economic-development marketing listing, last updated February 17, 2026, describes 5–20-acre parcels and quotes $95,000 per acre.16 Those are dated marketing terms, not independently confirmed current availability. Remaining acreage, utility capacity, permitted uses, access and any site commitments still need a fresh check with the authority.

This is industrial-site inventory, not a newly started construction project. It therefore belongs in the market's sites-and-capacity analysis without being counted as an additional filed, approved or started building in the project pipeline. The research process now requires monthly checks of industrial parks and publicly marketed authority land, including older sites with no new construction announcement.

Jobs: announcements and payroll

The industrial projects on this page that state a job count add up to about 500 jobs: Faith Technologies (200+), Vulcaflex (130), GMB USA (75), Yongsan (about 68), Shinhwa (20), and Channing Street Copper (about 15). Metro manufacturing employment was 7,500 in June 2026, unchanged from a year earlier.6 The announced jobs would add about 7 percent.

The metro added 2,700 jobs over that year, reaching 83,600. Leisure and hospitality added 1,100 of them, about four in ten.6 Announced jobs arrive over years. Payroll counts arrive monthly. The factories are coming, and the hiring will show up later. But 500 jobs against 14,000 homes says the homes are not following the factories. The university and people moving in are driving housing here.

Added October 26 (preliminary)

City permit and inspection records and Auburn University's September construction report move several projects forward.1014 The Mark broke ground in April and has permits for three buildings. Jordan-Hare's north end zone broke ground September 10. The university lists six academic projects under construction, led by the $100 million Thorne building; Comer Hall was 90 percent done in September. In Opelika, Townes of Hampshire on Frederick Road has eight residential buildings with passed framing inspections.

Two projects finished. East Alabama Health reports its 30-bed critical care addition complete and EAMC North, a 40-bed psychiatric hospital, open, both in 2026.12 They leave the active list.

Smaller ones on the permit map: Grand Junction, 28 townhomes with a restaurant and offices at 1027 East Glenn, and a residential second phase of the Judd Avenue mixed-use project at 538 Richland Road.14 We have not counted either in the totals.

New in October

Auburn's council approved a tax abatement on October 6 for Maxim, a maker of labels and packaging. Maxim plans an RFID and smart-label plant at 967 Stage Road, near Auburn University's RFID Lab: about $1.4 million in a 5,680-square-foot building.78 How many jobs it brings is not settled. See below.

The same meeting took up a $9.87 million contract with AGX Siteworx for the first phase of the North Donahue Drive widening, from Shug Jordan Parkway toward the Saugahatchee Creek bridge, and a separate $770,861 engineering agreement.8 That is a contract, not a road. North Donahue is the road The Foundry's connector will meet.

On October 8 the planning commission approved revised plats for Slaughters Reserve, a 58-lot plan with townhomes, and extended Shelton Mill Phase 4's conditional use.9 A revised plat or an extension moves a project along. It does not add one. We have not yet matched these against the projects already counted, so the totals above leave them out.

Still checking

October coverage so far: Auburn's council on October 6, its planning commission on October 8, the city's October 7 release, Auburn's public permit map (read October 26), one Opelika project's permit and inspection records, and Auburn University's September report. Opelika's other permits, Lee County, Smiths Station and the Lee County part of Phenix City are not yet read.

What we're watching

How we count: the pipeline includes filed, approved, and started projects in Auburn and Opelika. Planned developments count at their approved maximum. Project figures without a number here come from the list below, where each row carries its source. Percentages compare the pipeline with Census housing estimates and Alabama Department of Labor metro employment.

  1. U.S. Census Bureau, QuickFacts: Lee County, Alabama (housing units, July 1, 2025; building permits, 2025). Primary. Link · Checked October 2, 2026.
  2. Auburn Villager, Council approves plan for large, mixed-use development in north Auburn, March 5, 2026. Press, reporting meeting materials. Link · Checked October 2, 2026.
  3. Opelika Observer, Auburn council paves way for mixed-use development, March 3, 2026. Press. Link · Checked October 2, 2026.
  4. The Auburn Plainsman, Auburn City Council approves new development project, March 2026. Press. Link · Checked October 2, 2026.
  5. Auburn University, Auburn achieves historic gains in student retention, graduation, career placement, September 2025. Primary. Link · Checked October 2, 2026.
  6. Alabama Department of Labor, Nonagricultural wage and salary employment, Auburn-Opelika MSA, June 2026 (preliminary). Primary. Link · Checked October 2, 2026.
  7. City of Auburn, Global label manufacturer Maxim opening RFID facility in Auburn, October 7, 2026. Primary. Link · Checked October 11, 2026.
  8. City of Auburn, City Council meeting recording and agenda index, October 6, 2026. Primary; automated transcript, final minutes not yet read. Link · Checked October 11, 2026.
  9. City of Auburn, Planning Commission meeting recording and agenda index, October 8, 2026. Primary; plat attachments and written conditions not yet read. Link · Checked October 11, 2026.
  10. Auburn University Facilities Management, Capital Program Report, September 2026. Primary. Link · Checked October 26, 2026.
  11. Auburn University Facilities Management, Academic Year in Review 2025-2026 (Concourse Hall, p. 20). Primary. Link · Checked October 26, 2026.
  12. East Alabama Health, About us. Primary, undated. Link · Checked October 26, 2026.
  13. Greysteel, Construction financing for 235-unit Interlude Cottages, March 24, 2026; City of Auburn council minutes, July 22, 2025. Link · Minutes · Checked October 26, 2026.
  14. City of Auburn, Permit Map, all records read October 26, 2026; City of Opelika public records search. Primary. Link · Checked October 26, 2026.
  15. City of Opelika, Opelika Economic Development announces Opelika Innovation and Technology Park, January 21, 2020. Primary. Link · Checked November 1, 2026.
  16. City of Opelika Economic Development, Opelika Innovation & Technology Park marketing property listing, last updated February 17, 2026. Seller listing; current offers unverified. Link · Checked November 1, 2026.

What's shaping the area.

The larger projects: 100 or more homes or apartments, major commercial and mixed-use sites, industrial investment of $10 million or 50 jobs, and public projects of $10 million or more, plus smaller ones that change a main corridor. Smaller projects appear in the monthly issues.

Growth areaMostly addingHomes and townhomes in the pipelineApartment units in the pipeline
Southwest AuburnHomes8020
Technology Park WestIndustrial jobs00
Northwest AuburnHomes9480
North AuburnMixed use, schools, homes2,468655
Downtown Auburn and campusStudent beds, campus buildings367883
US 280, Pepperell and Tiger TownApartments, commercial, hospital1,377935
Downtown OpelikaInfill homes, public housing rebuild617252
North OpelikaHomes; industrial reuse1,4230
East OpelikaHomes1,1380
South OpelikaHomes, apartments1,593517

Homes and apartments (13)

ProjectSizeStatusLast changeSourceVerified
Perryman Hill Apartments
3655 Veterans Pkwy, Opelika
265 unitsApproved
Conditional use
Mar 2026Opelika PC minutes, March 24, 2026Sept 23, 2026
Tree Tops II
2908 Birmingham Hwy, Opelika
338 unitsApproved
Conditional use
Mar 2026Opelika PC minutes, March 24, 2026Sept 23, 2026
Bridgewater
Logan Dr, Opelika
541 lotsApproved
Preliminary plat. Council awarded $1.53M Bridgewater Boulevard contract July 7, 2026.
Jul 2026Opelika PC minutes, Oct 28, 2025
Opelika Observer, July 7, 2026
Sept 23, 2026
Woodhaven
Ridge Rd (Lee Road 390), Opelika
~624 lots on 304.5 acresApproved
PUD, Ordinance 027-25, Sept 16, 2025
Sep 2025Opelika Observer public notices, Sept 25, 2025Sept 23, 2026
Crawford Reserve
1300 block Crawford Rd, Opelika
~171 lots on 73.3 acresApproved
PUD, Ordinance 006-26, Feb 3, 2026
Feb 2026Opelika Observer public notices, Feb 9, 2026Sept 23, 2026
Mayfair
S Uniroyal Rd, Opelika
401 lots plannedApproved
Phases 1 and 2 preliminary plats (246 lots)
Jun 2026Opelika PC minutes, June 23, 2026Sept 23, 2026
Society Hill Apartments
2900 Society Hill Rd, Opelika
265 unitsApproved
Conditional use; 12-month extension approved Aug 25, 2026
Aug 2026Opelika PC minutes, Aug 25, 2026Sept 23, 2026
Springs at Opelika
3305 Gateway Dr, Opelika
252 units in seven three-story buildings, plus clubhouse; 13.5 acresStarted
Groundbreaking announced Aug 2026. Opelika issued building permits for the seven apartment buildings, clubhouse, mail kiosk and site Aug 28-31, 2026 (BPRES-002200 to 002209-2026). Contractor McShane reports completion expected January 2028.
Aug 2026Opelika Observer, Aug 11, 2026
McShane Construction, Sept 29, 2026
Opelika public records search (permits BPRES-002200 to 002209-2026)
Nov 6, 2026
The Mill (Pepperell Village)
1st and 2nd Aves at 24th St, Opelika
$125 million over ~10 years; 327 homes and townhomes; office, retail, food on ~41 acresApproved
PUD approved 2025; 183-lot plat filed Sept 22, 2026; city awarded $3.34M Mill Village roundabout contract July 7, 2026
Sep 2026The Bama Buzz, July 15, 2025
Opelika PC agenda, Sept 22, 2026
Sept 24, 2026
Ridgecrest redevelopment (Auburn Housing Authority)
945 N Donahue Dr, Auburn
$21 million; 106 units rebuilt as 176 (70 for seniors)Approved
Council approved city funding Feb 2026
Feb 2026Opelika Observer, Feb 23, 2026Sept 24, 2026
Interlude Cottages (Auburn Cottages)
1397 N Dean Rd, Auburn
235 to 243 rental cottages and duplexes (sources differ)Approved
Council approved the conditional use July 22, 2025 (Resolution 25-145). A $46 million construction loan closed in March 2026, with completion targeted for 2027. The city has issued 23 home permits (Sept to Oct 2026) and permits for leasing, fitness and maintenance buildings (May 2026).
Oct 2026Auburn council minutes, July 22, 2025
Greysteel, March 24, 2026
City of Auburn permit map
Oct 26, 2026
Townes of Hampshire
2650 Frederick Rd, near Tiger Town, Opelika
Eight residential buildings and an amenity building; 155 townhomes in older records (not yet confirmed)Started
Building permits issued Jan 3, 2026 (BPRES-003672 to 003683-2025 and BPC-003688-2025). City inspection records show passed foundation, framing and rough-in inspections through October 2026.
Oct 2026Opelika permit ENGP-000141-2025
Opelika public records search
Oct 26, 2026
1680 Corporate Drive apartments
1680 Corporate Dr, Opelika
Six apartment buildings, clubhouse, mail building and one other buildingFiled
Building permits applied for April 20, 2026 and still pending on Nov 6. Developer and unit count not yet confirmed.
Apr 2026Opelika public records search (permits BPRES-001347 to 001352-2026; BPC-001353, 001354, 001356-2026)Nov 6, 2026

Student housing and campus (6)

ProjectSizeStatusLast changeSourceVerified
LeMans Square and Chateau apartments
560 N Gay St and 560 Perry St, Auburn
Redevelopment; Chateau 126 unitsApproved
Council approved conditional uses Aug 18, 2026
Aug 2026Opelika Observer, Sept 1, 2026
Auburn PC agenda, Aug 13, 2026
Sept 23, 2026
RISE Auburn
712 W Glenn Ave, Auburn
240 units, 718 beds; $87 million permitApproved
Building permit issued (the city's permit map dates it May 27, 2026; press reported it June 3); foundation permit February 2026. Due before the 2028-29 school year. Start of construction not yet confirmed.
Jun 2026The Bama Buzz, June 8, 2026Sept 23, 2026
The Mark
141 Wright St, Auburn
329 units, 825 bedsStarted
Groundbreaking and start of construction reported April 15, 2026. City permits: foundations for Buildings 100 and 200 (March 2026), Building 200 (Aug 2026), Building 300 (Oct 7, 2026) and the Building 100 main building (BL-2025-04372, Nov 6, 2026). Delivery expected fall 2028.
Nov 2026The Bama Buzz, April 16, 2026
Landmark Properties, Dec 9, 2025
City of Auburn permit map
Oct 26, 2026
East Thach residence hall (Auburn University)
E Thach Ave at S Gay St, Auburn
680 to 696 new beds (sources differ); six stories, 170,000 SF; $100 million; replaces Cambridge HallStarted
Cambridge Hall demolished; site work and basement excavation under way, 5% complete (university report, September 2026). Completion March 2028.
Sep 2026Auburn University capital program report, Sept 2026 (p. 29)
Auburn University project profile
Auburn University, Nov 18, 2025
Oct 26, 2026
Jordan-Hare north end zone events center
Auburn University campus
~300,000 SF, seven stories; $323 million; events, dining, premium game-day spaceStarted
Groundbreaking Sept 10, 2026; site and foundation work under way. Full completion targeted spring 2029.
Sep 2026Auburn Athletics, Sept 11, 2026
Auburn University capital program report, Sept 2026
Auburn University, April 2026
Oct 26, 2026
Auburn University academic projects under construction
Auburn University campus
Thorne academic and research building $100M; Comer Hall renovation $40M; Quad halls Keller and Owen $28.5M; Research Park facility (RFID) $25M; Brown-Kopel lab $14.5M; airport control tower $9MStarted
University lists all six as under construction and its September report shows work on each. Comer Hall was 90% complete in September with a November 2026 target.
Sep 2026Auburn University capital projects
Auburn University capital program report, Sept 2026
Oct 26, 2026

Commercial and mixed-use (8)

ProjectSizeStatusLast changeSourceVerified
Perryman Hill Plaza
US 280 at Veterans Pkwy, Opelika
65,000 SF center; 9-lot platFiled
Plat back before the planning commission. Grocery anchor unconfirmed.
May 2026Opelika PC agenda, May 26, 2026Sept 23, 2026
Birmingham Hwy rezoning
3400 block, Opelika
18.34 acres, R-4 to C-2 (gateway corridor overlay)Approved
Council adopted Ordinance 022-26, July 7, 2026
Jul 2026Opelika council minutes, July 7, 2026
Opelika Observer, July 7, 2026
Sept 23, 2026
Extreme Powersports dealership
4800 Birmingham Hwy, Opelika
$9.2 million permitApproved
Building permit issued May 22, 2026
May 2026The Bama Buzz, May 26, 2026Sept 23, 2026
The Foundry at North College
N College St at Shug Jordan Pkwy, Auburn
282 acres; up to 2,425 homes (up to 625 apartments and 1,800 houses and townhomes); 275,000 SF commercial and 60,000 SF office; seven phases over 15 yearsApproved
Jolly Development. Council unanimously approved annexation, PUD zoning, the development plan and an infrastructure agreement March 3, 2026. Unit counts are maximums. Plains High School is planned next door.
Mar 2026Auburn Villager, March 5, 2026
Opelika Observer, March 3, 2026
The Auburn Plainsman, March 2026
Oct 2, 2026
Farmville mixed-use development
E Farmville Rd at US 280, Auburn
Mixed-use PDD (size not yet published)Filed
Rezoning and conditional use on July 9, 2026 agenda; council approved a Farmville mixed-use amendment Aug 18
Aug 2026Auburn PC agenda, July 9, 2026
Opelika Observer, Aug 18, 2026
Sept 24, 2026
Shug Jordan Commercial
Shug Jordan Pkwy at N Donahue Dr, Auburn
58.92-acre PDD; mixed useFiled
Annexation, rezoning and conditional use on April 9, 2026 agenda. Same area as The Foundry.
Apr 2026Auburn PC agenda, April 9, 2026Sept 24, 2026
Liv Smart hotel
2495 Interstate Dr, Opelika
Extended-stay hotel (room count not confirmed)Approved
Building permit issued Nov 13, 2025 (BPC-002125-2025); land-disturbance permit Feb 2025. Start of construction not yet confirmed.
Nov 2025Opelika public records search (permits BPC-002125-2025; ENGP-000307-2025)Nov 6, 2026
Hotel at 1680 Capps Landing
1680 Capps Landing, Opelika
Hotel (brand and size not public)Filed
Building permit applied for May 13, 2026 and still pending on Nov 6 (BPC-001714-2026). A land-disturbance permit for the site was applied for in March 2026.
May 2026Opelika public records search (permits BPC-001714-2026; ENGP-000706-2026)Nov 6, 2026

Industrial and data centers (6)

ProjectSizeStatusLast changeSourceVerified
Faith Technologies
Former Joann Fabrics distribution center, Opelika
$79 million; 200+ jobsApproved
Incentives. Start of work not confirmed.
Jul 2026WTVM, Feb 25, 2026Sept 23, 2026
Vulcaflex
3111 Haygood Ct, Auburn Technology Park West
~$70 million; 130 jobs; ~304,000 SF first phaseApproved
Council approved industrial conditional use Aug 18, 2026; site preparation reported
Aug 2026Opelika Observer, Aug 18, 2026Sept 23, 2026
Auburn Technology Park West expansions, 2026
Riley St, Haygood Ct, Biltmore Ln, Auburn
Shinhwa $37M, 20 jobs; 2A USA $32M; Duck Il ~$21M; Kamtec $9.2M; DIA, INFAC, Vertex permits; Seohan Plant #3 and KettenWulf requestsApproved
Mix of state announcements, city conditional uses and building permits
Aug 2026Made in Alabama: 2A USA, Aug 2026
Made in Alabama: Shinhwa, March 2026
Opelika Observer, March 3, 2026 (Shinhwa abatement, 20 jobs)
The Bama Buzz, July 6, 2026
Oct 2, 2026
Core Scientific data center expansion
1571 W Samford Ave, Auburn
Expansion inside an existing building ($55 million permit reported); Phase 3 and a new substation; staff from 11 to 20+Approved
City records: alteration permit for Phases 1 and 2 (Feb 2026), Phase 2 mechanical expansion and Phase 3 site plans (2026), substation permit (Aug 2026), Phase 3 foundation permit (Oct 7, 2026). Start of construction not yet confirmed.
Oct 2026WTVM, Feb 25, 2026
City of Auburn permit map
Oct 26, 2026
Opelika industrial incentives, 2026
Orr Industrial Park and others, Opelika
GMB USA $9M, 75 jobs; Yongsan $4.46M, ~68 jobs; BS Logistics $1.2M; Channing Street Copper ~$1M, ~15 jobsApproved
Council tax abatements and state announcements, April to July 2026
Jul 2026Opelika Observer, July 7, 2026
Made in Alabama: GMB USA, April 2026
Sept 24, 2026
Flex Opelika
2685 Society Hill Rd, Opelika
15 commercial flex buildingsApproved
Building permits applied for March 2026. Five were issued July 2 to Aug 11, 2026 (Buildings 1-4 and 15); ten were still pending on Nov 6. Land-disturbance permit issued Dec 2025. Start of building construction not yet confirmed.
Aug 2026Opelika public records search (permits BPC-000568 to 000582-2026; ENGP-003469-2025)Nov 6, 2026

Schools, hospital, and public works (2)

ProjectSizeStatusLast changeSourceVerified
Plains High School and new junior high (Auburn City Schools)
Plains High site: east of N Donahue Dr at Yarbrough Farms Blvd; other school works at separate locations
$241.8 million in warrants for schools and facilitiesApproved
Council approved Aug 4, 2026; high school expected to open fall 2028
Aug 2026Opelika Observer, Aug 11, 2026Sept 24, 2026
Opelika road contracts tied to new neighborhoods
Bridgewater Blvd; Hi-Pack Dr; Mill Village roundabout
$7.6 millionApproved
Council awarded contracts July 7, 2026
Jul 2026Opelika Observer, July 7, 2026Sept 24, 2026

How this is put together

Filed means on an agenda or in an application. Approved means a board or council voted yes; we name the step. Started means construction confirmed by the developer or the city. Every row carries a source and the date we last checked it.

Sources: Opelika Planning Commission and City Council; Auburn Planning Commission and City Council; the Opelika Industrial Development Authority; Lee County Commission (from later issues). Agendas and minutes are the primary record; press coverage fills in announcements and groundbreakings. We report what the record says and label what is not yet confirmed. This report is updated through the month; each month gets a new report.

See something we missed or got wrong? Tell us. How Redchip researches and verifies: Method.

Disclosure: the author is a partner in Vanguard Industrial Partners, which develops projects in this market and may have interests in or near properties listed here. General information only; see the disclaimer.

Changes this month