Texarkana, Texas and Arkansas

Updated November 1, 2026

Preliminary November report. Research is in progress. None of the four cities has a completed permit and inspection sweep. Meeting, capital-budget and procurement coverage is partial. This is not a complete inventory or a market-wide records-through date. Completed projects are retained for context.

Each dot is a project in the list below: filled when construction has started, solid ring when approved, dashed when only filed. Muted filled dots mark completed or opened projects. Light dotted rings mark proposed concepts. Tracts large enough to see are shown as a shaded circle of their stated acreage, centered on the project; it shows size, not the property line. Points use Census address matches where available. Campus points, the Hyatt location and highway markers are approximate context. Shared campus points do not locate individual proposed buildings. No pin represents a surveyed footprint. Click a dot or a project for its status and source. The table and map contain 21 projects and programs. Some are delivered, some are proposals. No combined investment, housing or active-construction total is calculated. TexAmericas Center and Red River Army Depot are outside this public table.

November 2026 · Preliminary report · Updated November 1

The short version

Texarkana has several different development stories. Amazon's Arkansas delivery station and Hyatt Studios on the Texas side have opened. TAMUT reports a completed academic building and continuing athletic construction, while planning more housing. Texas High's $59 million career and technical center opened in March, and a converted North State Line hotel now holds 113 apartments. Those deliveries and proposals should not be counted as one active construction pipeline.2, 9, 11, 38, 39

Pleasant Grove Surgical Hospital is a separate, newly filed hospital proposal at 3133 Pleasant Grove Road. Its July registration estimates $18 million for a 36,858-square-foot, two-story, six-bed facility. The table carries it as Filed: the submitted August 2026 start and August 2027 completion do not confirm construction. Potter Properties is the listed owner and BB&W Architects the designer.44, 45

The West Park hospital campus built for Wadley is a separate question, and its status is unconfirmed. A June guide describes it as unused and seeking an operator. An August Gazette headline says the property owner calls it finished and reports operator interest; we could not read that story. Neither completion nor an operator is confirmed, so it stays out of the table. Future dates in an accessibility registration do not make it an active project.18, 43

University Avenue and the Texas commercial corridors

The university's housing strategy describes a multi-phase Eagle Landing program. The system's second-quarter FY2026 update lists project 22-3482, Eagle Landing Phase 4, with a $51.8 million planning amount. Its older campus strategy and capital plan use different phase sizes and schedules. The table carries the expansion as Proposed while those records are reconciled. It does not turn a fall target into an opening or add phase budgets together.1, 3, 4

WoodSpring Suites has a July state registration for a 38,220-square-foot hotel on Piney Road. HomeGoods has a 30,600-square-foot tenant-improvement registration at Town West. These are documented filings. A submitted start date and an accessibility inspection are different from a confirmed construction start or store opening.8, 10

The sports investment is already partly delivered. The city's June 2025 report says the renovated Swanger complex opened that May. Parks Elementary and Dunbar also opened for the 2025 school year. They remain visible as recent changes to the market, outside active construction.16, 17

Downtown reuse

Landmark on Pine would put 40 senior apartments in historic buildings on Pine Street. TSAHC describes a total development budget near $16.1 million; the TDLR construction estimate is lower because it is a different measure. KTBS later reported an $18 million total that includes market-rate units and retail, with work to start in summer 2026 by removing asbestos and lead paint. The figures measure different things and are not reconciled. Neither projected start is proof work began. Nearby, the city reported construction at the Assembly Line incubator in March 2026. Its latest delivery date remains a follow-up item.5, 6, 7, 27, 42

The Arkansas side

KSLA reported Amazon operations in September 2025 and a ribbon cutting in February 2026. The ceremony is not the operational start date. Airport work has more than one track: an enacted $11 million federal appropriation supports taxiway and taxilane improvements. Separately, May 18 board minutes record a 5-0 vote authorizing a $15,786,713 Tatum Excavating agreement for the runway 4/22 extension, overlay and taxiway Delta extension. The Gazette's August 21 front page reports the first phase, a 500-foot extension and overlay, began July 20. It puts the three phases above $63 million with completion expected in 2027. That figure is reported, not added to the contract.11, 14, 33, 34, 40

The runway is being lengthened for large aircraft. In April, Dean Baldwin Painting and the airport announced a four-bay aircraft painting facility with 150 to 160 jobs. The August report names it the expected first tenant of the planned MRO site. No investment figure, building contract or start date has been found, so the table carries it as Proposed.40, 41

One housing delivery came from reuse rather than new building. KTBS reported the former America's Best Value Inn at 4200 North State Line reopened as ArTex Commons, 113 studio and one-bedroom apartments. The Gazette covered it in March 2025; the exact opening date is not in the story we reviewed.39

Two smaller housing leads need following even though they fall below the table's 50-home threshold. Local reporting describes a 40-lot Highlands subdivision on North Rondo Road. A September legal notice puts a 45-lot Autumn Creek final plat on the October planning agenda. A hearing notice does not establish its outcome.19, 20

The Arkansas street and drainage bond program is another material lead. The reported $29.41 million issue includes refunding as well as new capital work. We have not turned its face value into a new-construction total or assigned it to individual streets.22

Nash and Wake Village

Nash's July minutes record a utility-upgrade presentation and authorization to apply for a water grant. April 2025 minutes award the EDA disaster-improvements contract to Francis Excavating for $2,569,148.22, contingent on EDA approval. Separate April 2026 minutes correct the downtown revitalization award to $357,567.33, including both alternates. Neither record establishes completion.24, 35, 36

Wake Village's meeting and permit inventory is still open. No absence of projects is inferred from that gap. Its school renovation appears in the district's facilities plan; the current scope and completion remain research questions.32

Smaller projects and public land

The city's permit reports also capture restaurant alterations, offices, clinics and smaller residential addresses. Those records stay in the research register even when they do not enter the table. The 2025 annual report describes city land preparation in Falvey Industrial Park and the Pleasant Grove/Cooper Lane annexation service plan; parcel boundaries and overlapping actions still need reconciliation.7, 16, 26

Historic Orr School is a named priority site in a regional brownfields assessment grant. That supports environmental and reuse planning, not a committed building redevelopment or a construction start.21

Still checking

How we built it

The boundary covers both Texarkanas, Nash and Wake Village, and adjoining urban highway corridors in Bowie and Miller counties. It does not mean every part of both counties. TexAmericas Center and Red River Army Depot remain outside this public table. The locator on Home and Markets is schematic, not a coverage boundary.

This first pass combines independent city and corridor searches, Texas city quarterly and annual reports, university capital plans, state filings, transport programs, agency notices and local reporting. No market-wide records-through date is claimed. None of the four cities has a completed permit and inspection sweep. The meeting follow-up recovered legacy Texas records, 49 Arkansas board agendas, Nash records and Bowie County minutes. Agenda screening is further along than attachment and outcome review. Newer city portals, Wake Village records and Miller County downloads leave material gaps. The full 24-month meeting review, school capital budgets, utility and housing-authority records, procurement histories remain open. A separate pre-repository omission search added leads; its West Park searches were qualified by automatically supplied prior context. It is not an unqualified blind or exhaustive audit. These gaps limit the report's completeness.

The table distinguishes a plan, a filing, a named authorization, physical work reported on a source date and a delivery. It calculates no combined investment or housing total. Map points locate context; several campus projects share a campus point and do not imply a fixed building site.

Sources

  1. Texas A&M-Texarkana, housing and construction strategy. Public institutional plan; targets require later confirmation. Source. Checked October 31, 2026.
  2. Texas A&M-Texarkana, August 21, 2026 campus update. Institutional announcement. Source. Checked October 31, 2026.
  3. Texas A&M System, FY2026-2030 Texarkana capital plan, August 2025. System capital plan; includes unfunded needs. Source. Checked October 31, 2026.
  4. Texas A&M System, FY2026 second-quarter capital-plan changes. System planning update; not a construction permit. Source. Checked October 31, 2026.
  5. TSAHC, Landmark on Pine, March 13, 2026. Housing financier; original read in browser. Source. Checked October 31, 2026.
  6. TDLR, Landmark on Pine, registered January 13, 2026. Accessibility registration; dates are submitted schedules. Source. Checked October 31, 2026.
  7. Texarkana, Texas, March 2026 economic development report. City report; not a complete active-permit inventory. Source. Checked October 31, 2026.
  8. TDLR, WoodSpring Suites, registered July 7, 2026. Accessibility registration. Source. Checked October 31, 2026.
  9. Texarkana Today, Hyatt Studios opening, October 20, 2026. Local reporting. Source. Checked October 31, 2026.
  10. TDLR, HomeGoods, registered November 13, 2025. Accessibility registration and inspection status. Source. Checked October 31, 2026.
  11. KSLA, Amazon ribbon cutting, February 18, 2026. Local reporting with company comments. Source. Checked October 31, 2026.
  12. AR-TX REDI, Amazon project announcement, September 20, 2024. Economic development announcement. Source. Checked October 31, 2026.
  13. TxDOT, I-30 construction traffic update, June 2026. State construction notice. Source. Checked October 31, 2026.
  14. Rep. Nathaniel Moran, airport appropriation, February 5, 2026. Federal funding announcement. Source. Checked October 31, 2026.
  15. ARDOT, SFY2026 third-quarter highway report, as of March 31, 2026. State program; scheduled projects distinguished from awards. Source. Checked October 31, 2026.
  16. Texarkana, Texas, June 2025 economic development report. City report; scanned pages read with OCR. Source. Checked October 31, 2026.
  17. KSLA, Parks and Dunbar school openings, August 6, 2025. Local completion reporting. Source. Checked October 31, 2026.
  18. Texarkana Today, medical guide on the West Park campus, updated June 2026. Local reporting; current operator and work status need follow-up. Source. Checked October 31, 2026.
  19. Texarkana Today, Arkansas subdivision and store, June 2026. Local reporting of planning actions. Source. Checked October 31, 2026.
  20. Published planning notice, September 27, 2026. Legal notice; establishes October hearing request only. Source. Checked October 31, 2026.
  21. ATCOG, brownfields assessment grant, July 28, 2026. Regional grant announcement. Source. Checked October 31, 2026.
  22. Texarkana Today, Arkansas street and drainage bonds, June 2, 2026. Reported financing action. Source. Checked October 31, 2026.
  23. Texarkana, Arkansas, August 17, 2026 board agenda. Agenda; final actions not inferred. Source. Checked October 31, 2026.
  24. Nash, July 13, 2026 council minutes. Approved minutes. Source. Checked October 31, 2026.
  25. U.S. EDA, Nash Business Park access grant, April 17, 2024. Federal award; latest construction status pending. Source. Checked October 31, 2026.
  26. Texarkana, Texas, 2025 annual report. City annual report. Source. Checked October 31, 2026.
  27. TDLR, Assembly Line registration, November 3, 2025. Accessibility registration. Source. Checked October 31, 2026.
  28. TDLR, TAMUT baseball and softball, July 17, 2026. Accessibility registration. Source. Checked October 31, 2026.
  29. Monarch Private Capital, Ridge at Texarkana. Investor description; no current construction date. Source. Checked October 31, 2026.
  30. MyTown, copied Texas city agendas. Secondary agenda copy; original and outcomes need checking. Source. Checked October 31, 2026.
  31. KSLA, Fairview groundbreaking, February 17, 2026. Local reporting; completion-year conflict requires checking. Source. Checked October 31, 2026.
  32. Texarkana ISD, Imagine 2026 facilities-plan review, October 2024. District plan; target dates are not actual completion. Source. Checked October 31, 2026.
  33. KSLA, Amazon operations and hiring, September 2025. Local reporting; article retains conflicting opening-date wording. Source. Checked November 1, 2026.
  34. Texarkana Arkansas, May 18, 2026 board minutes, approved June 1. Recorded vote for Resolution 2026-54. Source. Checked November 1, 2026.
  35. Nash, April 10, 2025 council minutes. Award contingent on EDA approval. Source. Checked November 1, 2026.
  36. Nash, April 27, 2026 council minutes. Corrected downtown contract award and alternates. Source. Checked November 1, 2026.
  37. Texarkana Texas, September 14, 2026 council packet, pages 127-135. Proposed ordinance and supporting material; later outcome unconfirmed. Source. Checked November 1, 2026.
  38. KSLA, Texarkana ISD CTE Innovation Center opening, March 20, 2026. Local reporting with district figures. Source. Checked November 1, 2026.
  39. KTBS, ArTex Commons opening. Local reporting; publication date not shown. Source. Checked November 1, 2026.
  40. Texarkana Gazette, front page, August 21, 2026. Local reporting on the runway phases and MRO tenant. Source. Checked November 1, 2026.
  41. Texarkana Today, Dean Baldwin Painting announcement, April 22, 2026. Local reporting of a company and airport announcement. Source. Checked November 1, 2026.
  42. KTBS, Landmark on Pine construction outlook, 2026. Local reporting; projected start, not confirmed work. Source. Checked November 1, 2026.
  43. Texarkana Gazette, "Hospital operators showing interest in finished former Wadley project, property owner says," August 5, 2026. Headline only; article not readable to our tools. Source. Checked November 1, 2026.
  44. TDLR, Pleasant Grove Surgical Hospital, registered July 1, 2026. Primary print-format filing; dates are submitted schedules. Source. Checked November 1, 2026.
  45. Texarkana Today, surgical hospital proposal, July 2, 2026. Local reporting based on the filing. Source. Checked November 1, 2026.
  46. Texarkana Magazine, October 2026, page 44. Reported phased Nash school reuse; hotel date is projected. Source. Checked October 31, 2026.
  47. Texarkana Texas, Project Maps. Official proposed State Line and Hazel corridor description; undated. Source. Checked November 1, 2026.
  48. TDLR, Sunset Apartments, registered May 27, 2026. Rehabilitation filing, not proof of physical start. Source. Checked October 31, 2026.
  49. Muyni, reproduced Texarkana Texas December 8, 2025 agenda. Site plan listed as a first briefing, not a recorded adoption. Source. Checked November 1, 2026.
  50. Muyni, reproduced Texarkana Texas January 12, 2026 agenda. Scheduled hearing/vote, not its outcome. Source. Checked November 1, 2026.

What's shaping the area.

50 homes or apartments, 150 student beds, 20,000 commercial square feet or five corridor acres, industrial investment of $5 million or 25 jobs, public projects of $5 million, or 25 acres rezoned. Smaller corridor and landmark reuse projects may appear. Thresholds govern prominence; research captures smaller leads too.

Housing and downtown homes (3)

ProjectSizeStatusLast changeSourceVerified
Eagle Landing housing expansion
University Avenue, Texas A&M-Texarkana
Phase 4 system planning amount $51.8M; other phases under reviewProposed
System project 22-3482 carries a $51.8M Phase 4 planning amount in the FY2026 second-quarter update. The older campus strategy and 2025 capital plan use different phase sizes and schedules. These are not added together. A current construction start is unconfirmed. Campus context point, not a housing footprint.
Aug 2026Texas A&M-Texarkana, housing and construction strategy
Texas A&M-Texarkana, August 21, 2026 campus update
Texas A&M System, FY2026-2030 Texarkana capital plan, August 2025
Texas A&M System, FY2026 second-quarter capital-plan changes
Nov 1, 2026
Landmark on Pine
301-319 Pine Street, downtown Texarkana TX
40 senior apartments; financier reports nearly $16.1M total budgetFiled
TDLR registration covers adaptive reuse. The financier gives a 2026 target start and late-2027 target completion. Physical work has not been confirmed in this review. Address point marks one end of the building group. KTBS reported construction expected to begin in summer 2026, starting with asbestos and lead-paint removal, and an $18 million total including market-rate units and retail space. Budget figures differ by source and are not reconciled.
Jan-Mar 2026TSAHC, Landmark on Pine, March 13, 2026
TDLR, Landmark on Pine, registered January 13, 2026
KTBS, Landmark on Pine construction outlook, 2026
Oct 31, 2026
ArTex Commons
4200 North State Line Avenue, Texarkana AR
113 apartments in a converted hotelComplete
KTBS reported the former America's Best Value Inn reopened as ArTex Commons, 113 studio and one-bedroom units operated by Dels Corp. The Gazette covered the complex in March 2025. The exact opening date is not stated in the reviewed story. Delivered housing; excluded from active construction. Census-geocoded address point.
2025KTBS, ArTex Commons opening
Texarkana Gazette, North State Line apartments, March 19, 2025 (headline only; page not readable to our tools)
Nov 1, 2026

Campus and schools (6)

ProjectSizeStatusLast changeSourceVerified
RRCU Athletic Complex
University Avenue, TAMUT, Texarkana TX
Baseball, softball and other phased athletic facilitiesStarted
The university reported ongoing construction in August. The baseball/softball filing lists an $18.4M construction estimate; system program budgets cover different scopes and are not added together. Approximate campus context point; the 7701 University address did not geocode.
Aug 2026Texas A&M-Texarkana, August 21, 2026 campus update
Texas A&M System, FY2026-2030 Texarkana capital plan, August 2025
Texas A&M System, FY2026 second-quarter capital-plan changes
TDLR, TAMUT baseball and softball, July 17, 2026
Oct 31, 2026
James C. Morriss Business, Engineering and Technology Building
7101 University Avenue, TAMUT, Texarkana TX
System capital-plan budget about $44.9MComplete
The university reported completion in August 2026. Campus address point gives context rather than an exact building footprint.
Aug 2026Texas A&M-Texarkana, August 21, 2026 campus update
Texas A&M System, FY2026-2030 Texarkana capital plan, August 2025
Oct 31, 2026
TAMUT storm shelter / safe room
Texas A&M-Texarkana campus
About $16.4M proposed planning amountProposed
The August 2025 capital plan makes progress conditional on FEMA requirements, the program of requirements and financing. Current funding and siting have not been confirmed. Approximate main-campus context point.
Aug 2025Texas A&M System, FY2026-2030 Texarkana capital plan, August 2025Oct 31, 2026
Parks Elementary
1915 Pine Street, Texarkana TX
Replacement elementary campusComplete
Local reporting confirms students attended in August 2025. This is a delivery within the baseline period, excluded from active construction.
Aug 2025KSLA, Parks and Dunbar school openings, August 6, 2025
School address
Oct 31, 2026
Paul Laurence Dunbar Early Education Center
2500 College Drive, Texarkana TX
New early-education campusComplete
Local reporting confirms opening for the August 2025 school year. The current school and chamber opening notice identify College Drive; older state directory information used a different address.
Aug 2025KSLA, Parks and Dunbar school openings, August 6, 2025
Current school address
Chamber opening notice
Oct 31, 2026
Texas High CTE Innovation Center
4001 Summerhill Road, Texarkana TX
About $59 million, 2022 bondComplete
KSLA reported the official opening on March 19, 2026, with district use since winter. Officials put construction cost near $59 million. Address point is the Texas High School campus, not the building footprint.
Mar 2026KSLA, CTE Innovation Center opening, March 20, 2026Nov 1, 2026

Commercial and downtown reuse (5)

ProjectSizeStatusLast changeSourceVerified
The Assembly Line
215 Pine Street, downtown Texarkana TX
13,000 SF reuse; $1.8M TDLR construction estimateStarted
The city reported physical work in March 2026. Later delivery and the scope of subsequent procurement still need checking. Included below the size threshold for downtown reuse and its regional business-incubator role.
Mar 2026Texarkana, Texas, March 2026 economic development report
TDLR, Assembly Line registration, November 3, 2025
Oct 31, 2026
WoodSpring Suites
902 Piney Road, Texarkana TX
38,220 SF hotel; $4.35M submitted construction estimateFiled
TDLR registration sets an August 2026 start target and June 2027 finish target. Those dates do not establish physical construction or a city building permit.
Jul 2026TDLR, WoodSpring Suites, registered July 7, 2026Oct 31, 2026
Hyatt Studios
2401 University Avenue, Texarkana TX
121 suites, reportedComplete
Local reporting says the hotel opened July 10, 2026, before its October ribbon cutting. The address did not geocode; approximate University/I-30 context point.
Jul-Oct 2026Texarkana Today, Hyatt Studios opening, October 20, 2026Oct 31, 2026
HomeGoods at Town West
2315 Richmond Road, Suite 1E, Texarkana TX
30,600 SF tenant improvements; $1.5M submitted estimateFiled
TDLR shows accessibility inspection complete. A store opening or city occupancy certificate has not been confirmed; accessibility status is not treated as proof of either. The map point is the shopping-center street address.
Nov 2025 filingTDLR, HomeGoods, registered November 13, 2025Oct 31, 2026
Pleasant Grove Surgical Hospital
3133 Pleasant Grove Road, Texarkana TX
$18M estimated; 36,858 SF; two stories; six bedsFiled
Registered July 1, 2026 as TABS2026024260. The filing lists Potter Properties Inc. as owner and BB&W Architects LLC as designer. Its August 3, 2026 start and August 2, 2027 completion are submitted schedules; physical construction is unconfirmed. The site-plan outcome remains under review. Census-geocoded address point, not a building footprint.
Jul 2026TDLR, Pleasant Grove Surgical Hospital, registered July 1, 2026
Texarkana Today, surgical hospital proposal, July 2, 2026
Nov 1, 2026

Industry and logistics (2)

ProjectSizeStatusLast changeSourceVerified
Amazon last-mile station
4400 East 19th Street, Texarkana AR
50,000 SF; about 100 workers reported in February 2026Complete
KSLA reported operations in September 2025 and a ribbon cutting in February 2026. The ceremony is not the operational start date. Completed delivery station; excluded from active construction. Address point marks the facility.
Sep 2025 / Feb 2026KSLA, Amazon ribbon cutting, February 18, 2026
AR-TX REDI, Amazon project announcement, September 20, 2024
KSLA, Amazon operations and hiring, September 2025
Nov 1, 2026
Dean Baldwin Painting aircraft facility
Texarkana Regional Airport, Arkansas
Four paint bays; 150 to 160 jobs announcedProposed
The company and the airport announced the facility in April 2026. The August Gazette front page names it the expected first tenant of the planned MRO site. No investment amount, construction contract or start has been verified. Airport address point gives context.
Apr 2026Texarkana Today, Dean Baldwin Painting announcement, April 22, 2026
KKYR, Dean Baldwin Painting jobs, April 22, 2026
Texarkana Gazette, August 21, 2026 front page
Nov 1, 2026

Roads, utilities and public works (5)

ProjectSizeStatusLast changeSourceVerified
I-30 Texas widening
I-30 through Nash and Texarkana TX
Interstate widening and access changesStarted
TxDOT describes work in progress and traffic shifts in June 2026. Approximate FM 989 / Kings Highway corridor point represents the project, not its full contract limits.
Jun 2026TxDOT, I-30 construction traffic update, June 2026Oct 31, 2026
Airport taxiway and taxilane improvements
Texarkana Regional Airport, Arkansas
Enacted $11M federal appropriationApproved
Congressional announcement confirms federal funding, not a construction award or physical start. Separate from the runway 4/22 extension. Airport address point represents the airport, not the future work footprint.
Feb 2026Rep. Nathaniel Moran, airport appropriation, February 5, 2026Oct 31, 2026
I-30 Arkansas: state line to I-49
Texarkana AR, I-30
Job 030575; $40M-$50M scheduled bid estimateProposed
ARDOT scheduled the project for 2027 in its March 2026 report. A current letting or award has not been confirmed. Approximate corridor point, distinct from the Texas contract.
Mar 2026ARDOT, SFY2026 third-quarter highway report, as of March 31, 2026Oct 31, 2026
Swanger Sports Complex renovation
Spring Lake Park, 4303 North Park Road, Texarkana TX
$9.4M city-reported renovationComplete
The June 2025 city report says the renovated complex opened in May. A later parks guide gives a different cost; this row retains the dated city report figure. Point marks the park address, not a field boundary.
May 2025Texarkana, Texas, June 2025 economic development reportOct 31, 2026
Airport runway 4/22 extension, overlay and taxiway Delta extension
Texarkana Regional Airport, Arkansas
$15,786,713 Tatum Excavating agreementStarted
May 18 board minutes record Resolution 2026-54 adopted 5-0 for the Tatum agreement. The Gazette's August 21 front page reports Phase 1, the 500-foot extension and overlay, began July 20, with completion of all three phases expected in 2027. Later phases for MRO site work and taxiway changes are planned, not started. The $63 million three-phase figure is reported, not added to this contract. Separate from the $11M taxiway appropriation. Airport address point gives context, not the work limits.
Jul 2026Texarkana Arkansas, May 18, 2026 board minutes, approved June 1
Texarkana Gazette, August 21, 2026 front page
Nov 1, 2026

How this is put together

Proposed: publicly described plan. Filed: documented application or registration, without a verified approval or start. Approved: the named authorization, including funding where stated; not necessarily a building permit. Started: physical work reported in the cited source on its date. Complete: opening or completion reported, excluded from active-construction totals. Checked dates record source review, not a fresh site inspection.

Sources: City and agency reports; university and system capital plans; state registrations and transport notices; institutional announcements and attributed local reporting. Baseline meeting and permit inventories remain incomplete. Agendas and minutes are the primary record; press coverage fills in announcements and groundbreakings. We report what the record says and label what is not yet confirmed. This report is updated through the month; each month gets a new report.

See something we missed or got wrong? Tell us. How Redchip researches and verifies: Method.

Disclosure: the author is a partner in Vanguard Industrial Partners, which develops projects in the Southeast and may pursue opportunities involving projects covered here. This report uses public sources; development discussions do not determine project inclusion or status. General information only; see the disclaimer.