The short version

  • West Point replatted the former Coca-Cola property on East 10th Street by I-85 into three parcels "for future development" on August 10. The Development Authority's concept is a hotel with mixed use around it.1
  • Valley approved a project agreement for "Project Ironclad" on August 24. The city has not said what it is. It is one of five Valley project agreements since December 2025 whose end use is not public.2
  • The new Chambers County High School in Valley is about a $90 million job with much of the site work done. The county commission split 3-3 on matching Valley's $1.5 million safety net.3

Status labels

Filed on an agenda or in an application · Approved a board or council voted yes · Started construction confirmed by the developer or the city. Every entry shows its source and the date we last checked it.

About this market

The Greater Valley is three small cities on two sides of the Chattahoochee: Valley and Lanett in Chambers County, Alabama, and West Point in Troup County, Georgia. They share a labor pool, a trade area, one newspaper, and the Kia Georgia plant at I-85 exit 6. LaGrange, 15 miles north, is its own market and is not covered here. This is the first issue. The ledger below is the baseline from October 2024 on; "New this month" covers August 2026, the latest month with posted records.

New this month

Former Coca-Cola site Approved: replat

East 10th Street near I-85, West Point

The council approved the West Point Development Authority's replat of the site into three parcels, to "better configure and situate the three parcels for future development." The Authority's concept for the site is a hotel anchor with mixed use. No size or developer has been published.1

Source 1 · Verified Sept 24, 2026

Project Ironclad Approved: project agreement

Valley · site not public

Resolution 2026-105R approved a project agreement, pending the city attorney's review. The Chambers County Development Authority told the council the due-diligence period is six months. The end use, size, and site are not public, so it is not on the ledger yet.2

Source 2 · Verified Sept 24, 2026

Changes to projects we track

Chambers County High School Started

Ram Stadium Drive, Valley · about $90 million

The combined high school for Valley and LaFayette broke ground in 2024.4 In late August WTVM reported much of the site work finished and architectural plans due the next month, with opening then expected in 2029. The Chambers County Commission split 3-3 on a resolution to match Valley's $1.5 million contribution, money meant to cover a shortfall if one comes.3

Sources 3, 4 · Verified Sept 24, 2026

Speedway / 7-Eleven Started: open

2011 East 10th Street, West Point · about $8 million

The council approved the site plan in June 2025: a 5,000-square-foot store on about 7 acres.6 Both local papers have since reported the ribbon cutting for West Point's first Speedway.5

Sources 5, 6 · Verified Sept 24, 2026

Lanett Regional Airport Approved: grants

Lanett

ALDOT listed two apron expansion grants for Lanett on July 30, together $500,496, nearly all of it federal.7 Separately, a hangar group is taking deposits on 10 to 20 T-hangars; the city approved the ground lease earlier this year.8 We have not confirmed that work has started.

Sources 7, 8 · Verified Sept 24, 2026

The ledger

Larger projects we follow from month to month, as of this issue. The Greater Valley page always shows the current version.

ProjectSizeStatusLast changeVerified
Camellia Crossing
1002 Crossing Court East, Valley, AL
350+ homes planned (Alabama Power, 2022); Phase 1 was 28 homes; Phase 2 now sellingStarted
Phase 2 is selling and the developer identifies quick-move homes as under construction.
Sep 202691011Sept 24, 2026
Crowne Home Development / Kobeck Properties
King Road / Crown Homes, Valley, AL
Active new-construction subdivision; total buildout not verifiedStarted
Current builder marketing shows new construction; city records show multiple Kobeck/Crowne land and project actions.
Sep 20261213Sept 24, 2026
30th Street Residential Development
30th Street, Valley, AL
256-acre city residential holding; first 7 Newton/Wallace homes marketedStarted
New-construction homes are being marketed; city records show a much larger residential land and infrastructure program.
Apr 20261415Sept 24, 2026
King's Way Senior Housing
King Road & 55th Street W, Valley, AL
56 senior apartmentsStarted
Groundbreaking held Sept. 4, 2025; construction financed as 56 units of new senior housing.
Sep 20251617Sept 24, 2026
West Point Village Phase II
1650 10th St, West Point, GA
72 apartments: 55 LIHTC and 17 market-rateFiled
City support letter approved for the tax-credit application; final award/financing not confirmed.
May 202618Sept 24, 2026
West Point Hills
3rd / 4th Avenue area, West Point, GA
Developer says hundreds of homes across 3 phases; exact count not yet verifiedApproved
City approved a project-related parcel sale; developer materials describe a three-phase housing community.
May 20261819Sept 24, 2026
Safe Truck Parking Solutions
523 Warner Road, West Point, GA
25.59-acre truck-parking siteApproved
Annexation and MXD-1 rezoning approved.
Dec 202420Sept 24, 2026
Speedway / 7-Eleven – East 10th Street
2011 E 10th St, West Point, GA
~$8M; ~5,000 SF on ~7 acresStarted
Site plan approved June 2025; store opened with a ribbon cutting in 2026 (exact date not yet read).
202665Sept 24, 2026
Chambers Troup Group Expansion
Shawmut mill building, Valley, AL
Shawmut HQ / second plant; prior announced scale $14.58M and 80 jobsStarted
Shawmut opening reported Aug. 6, 2025. Investment/jobs are project-scale figures from the 2024 announcement, not a new 2025/26 announcement.
Aug 202521Sept 24, 2026
West Point Park / Tacko Construction
3003 Kia Pkwy, West Point, GA
31-acre, four-building industrial campus; first building 104,000 SFStarted
City work-session minutes reported site work under way.
Sep 202522Sept 24, 2026
Kia Georgia Solar & Hail-Protection Canopy
7777 Kia Parkway, West Point, GA
3.2M SF hail canopy with 10 MW of on-site solarStarted
Project completed; ribbon cutting announced April 24, 2026.
Apr 202623Sept 24, 2026
Old Lanett Mill Site Rezoning
Old Lanett Mill site, Lanett, AL
27-acre former mill redevelopment siteApproved
City approved the October 2024 zoning ordinance; redevelopment program remains open.
Oct 20242425Sept 24, 2026
Hotel Anchor & Mixed-Use / Former Coca-Cola Site
E 10th St near I-85, West Point, GA
Three-parcel hotel-anchor / mixed-use redevelopment; size not yet publishedApproved
Council approved the replat after the Development Authority advanced a hotel-anchor/mixed-use concept.
Aug 20261Sept 24, 2026
Chambers County High School
Ram Stadium Drive, Valley, AL
~$90M combined county high schoolStarted
Much of the site work was reported complete; a funding gap remains and completion was then targeted for 2029.
Aug 202634Sept 24, 2026
Lanett Regional Airport Expansion
Lanett Regional Airport, Lanett, AL
$500,496 apron grants plus 10–20 planned ~1,050-SF T-hangarsApproved
Apron grants awarded and hangar ground-lease path approved/signed; physical start not yet confirmed.
Jul 202678Sept 24, 2026

What we're watching

What are Valley's unnamed projects? Since December 2025 the Valley council has approved five project agreements whose end use is not public: Project Stripe, which came with an incentive and road work; Project Bear, with a property sale; Newmor Construction, with an annexation; an agreement with Brandon Powell; and now Project Ironclad.2 Code names are normal while a company is still choosing a site. Together they may matter more than anything on the ledger. Too early to call.

How much housing is Valley really adding? Four Valley housing projects are under construction, and the city holds 256 acres on 30th Street for residential development.15 Camellia Crossing was announced in 2022 with a plan for more than 350 homes.10 Plans are not counts, though. Until plats or permits show totals, we report what is confirmed. Watching.

Is the I-85 exit 2 corridor turning over? The Speedway is open, the former Coca-Cola site is replatted for a hotel concept, and 72 apartments are seeking tax credits just west of it on 10th Street.1518 Watching.

What we left off. Daesol Ausys Georgia announced a $72 million, 140-job plant in West Point in 2023.26 It is operating, but we found no new real-estate step since October 2024, so it is background here, not a ledger row.

Coverage this month

Valley council minutes are covered through August 24, 2026; September's were not yet posted. Valley's planning commission does not post agendas or minutes online, so its items appear here once they reach the council. Lanett posts council minutes about two months late and posts no agendas; coverage runs through July 20, 2026. West Point council minutes are covered through August 10, 2026; the September packet is a scan and was not read. Chambers County Commission agendas were checked through July 2026; its minutes are scans. Troup County, Harris County, and Georgia's regional-impact filings were checked for the West Point edge and turned up nothing new. If you see something we missed or got wrong, tell us and we will correct it in the next issue.

Sources and disclosure

  1. City of West Point, Council Meeting Minutes, August 10, 2026. Primary. Link · Checked September 24, 2026.
  2. City of Valley, City Council Minutes, August 24, 2026. Primary. Link · Checked September 24, 2026.
  3. WTVM, Chambers County school board hits funding setback on new high school, August 27, 2026. Press. Link · Checked September 24, 2026.
  4. WTVM, Chambers County School District breaks ground on new combined Chambers County High School, February 24, 2024. Press. Link · Checked September 24, 2026.
  5. LaGrange Daily News, Ribbon cut for West Point's first Speedway, 2026. Press. (The Valley Times-News ran the same story.) Link · Checked September 24, 2026.
  6. City of West Point, Council Meeting Minutes, June 9, 2025. Primary. Link · Checked September 24, 2026.
  7. Alabama Department of Transportation, ALDOT Alabama airport grants 2026, July 30, 2026. Primary. Link · Checked September 24, 2026.
  8. Lanett Airport Hangar Association, Lanett Regional Airport T-hangars, 2026. Developer. Link · Checked September 24, 2026.
  9. Holland Homes, Camellia Crossing, 2026. Developer. Link · Checked September 24, 2026.
  10. Alabama Power, Valley is home to Camellia Crossing, Alabama's first rural Smart Neighborhood, May 2022. Utility partner. Link · Checked September 24, 2026.
  11. City of Valley, City Council Minutes, August 25, 2025. Primary. Link · Checked September 24, 2026.
  12. Crown Homes Subdivisions, Crown Homes, Valley, 2026. Developer. Link · Checked September 24, 2026.
  13. City of Valley, City Council Minutes, June 9, 2025. Primary. Link · Checked September 24, 2026.
  14. Terri Kelley, Realtor, Newton & Wallace, Inc.: 30th Street, 2026. Developer marketing. Link · Checked September 24, 2026.
  15. City of Valley, Financial Statements, Fiscal Year Ended September 30, 2024 (management's discussion, p. 9), 2025. Primary. Link · Checked September 24, 2026.
  16. The LaFayette Sun, Groundbreaking ceremony held for senior housing project, September 2025. Press. Link · Checked September 24, 2026.
  17. CAHEC, 2025 Properties Closed, 2025. Lender. Link · Checked September 24, 2026.
  18. City of West Point, Council Meeting Minutes, May 11, 2026. Primary. Link · Checked September 24, 2026.
  19. West Point Hills, About us, 2026. Developer. Link · Checked September 24, 2026.
  20. City of West Point, Council Meeting Minutes, December 9, 2024. Primary. Link · Checked September 24, 2026.
  21. Chambers County Development Authority, Shawmut welcomes Chambers Troup Group, August 6, 2025. Primary. Link · Checked September 24, 2026.
  22. City of West Point, Council Work Session Minutes, September 30, 2025. Primary. Link · Checked September 24, 2026.
  23. Kia America, VPS and Kia Georgia complete landmark automotive hail-protection and solar canopy project, April 24, 2026. Company. Link · Checked September 24, 2026.
  24. City of Lanett, Council Documents (October 2024 minutes, Ordinance 10-24-01). Primary. Link · Checked September 24, 2026.
  25. City of Lanett, Council Meeting Minutes, June 6, 2016 (mill property size). Primary. Link · Checked September 24, 2026.
  26. Office of the Governor of Georgia, Automotive supplier Daesol Ausys Georgia to invest $72 million, August 29, 2023. Primary. Link · Checked September 24, 2026.

How Redchip researches and verifies: Method. Disclosure: neither Vanguard Industrial Partners nor Arkvera Grove Partners has an interest in any project or property in this market. The author is a partner in Vanguard, which develops projects elsewhere in the Southeast.

This is general information, not advice about a specific company, property, or transaction. See the disclaimer.

Get the next issue when it posts.

The Docket and new Redchip research by email, free. Unsubscribe any time.