We track what was proposed, what cleared, what stalled, and what got built in Statesboro, Brooklet, and Bulloch County, and Metter and Candler County, along I-16. Every entry carries a source and the date we last checked it.
On an agenda or in an application. Proposed, not yet decided.
A board or council voted yes. We name the step: rezoning, plat, conditional use, or incentives.
Construction confirmed by the developer or the city.
The read · October 2, 2026
Bulloch County had 86,949 people and 36,248 housing units in 2025, up 9.2 percent in population since 2020. Candler County had 11,275 people, up 2.5 percent.1 Since April 2025, councils and commissions here have approved about 1,700 homes and apartments with published counts, across six projects: Old Register Road (1,173), Herman Rushing Road (198), the Hunnicutt subdivision (134), the Coca-Cola site (108), Maria Sorrell Road (66), and East Olliff Street (19).2422 That is about 5 percent of Bulloch's housing, or a little over a year of construction at 2025's pace of 1,389 permits.1 Add the other units the city counts in its southeast corridor and Brooklet's 300-acre annexation, and the pipeline is about 3,300 units: nearly a tenth of the county's housing.67 Approved is not built.

One project is most of the recent approvals. In August 2025 Statesboro annexed 99.53 acres and expanded a planned development on Old Register Road and US 301 South to 237.59 acres. The plan shows about 1,173 units: some 500 apartments, 225 student cottages, 202 townhomes, and 246 houses, with a hotel, offices, a bank, and retail.23 That is about 70 percent of everything approved since April 2025. It sits between the campus and the interchange, which is where the market's two engines meet.

The Bulloch County Commission denied at least 165 rural subdivision lots in 2025 and approved about 200.4 In February 2026 it froze all residential rezonings while it writes an impact fee ordinance, and the freeze now runs through December 31.5 Over the same stretch, Statesboro approved about 1,500 units, most through annexation. Growth that would have spread across the county is landing inside the city, where there is water and sewer. Roads are the cost. The city counts about 1,342 units planned in the Burkhalter and Cawana corridor and has about $8.9 million in roundabouts and widening planned there, with the county sharing costs.6

Hyundai's Metaplant, east on I-16 in Bryan County, had hired 4,365 of its promised 8,500 workers by June 2026. Three of its suppliers sit along US 301 South. Two had hired 698 of the 1,086 jobs they promised: Ajin and Joon Georgia 430, Ecoplastic 268.8 The third, Hanon Systems, announced 160 jobs and lists its Statesboro plant among its production sites; it has not published a headcount.23 The county keeps preparing land: a $1.5 million state grant to make a 69-acre site in Gateway Park pad-ready.9 Two question marks sit nearby. The Aspen Aerogels plant at the interchange was abandoned half-built in February 2025.10 The $200 million revalyu recycling plant in Gateway park broke ground in 2023 with phase one due in late 2025; we have found no report on whether it is running.24

Two Hyundai suppliers announced 500 jobs at Metter's I-16 industrial park, DAS with 300 and Doowon with 200.1112 Candler County's employers counted 2,289 jobs in 2023, so the announcements would add about a fifth. The county recorded 7 new housing units permitted in 2025.1 If those jobs materialize and housing production stays that low, Metter would likely depend heavily on workers commuting from outside the city. The industrial park is getting a state grant to renew its certification and expand, and the city is weighing a 46-acre annexation at the exit.1314

Statesboro rezoned 26.49 acres on Burkhalter Road for a 230,000-square-foot data center. A fiscal study puts it at $1.2 billion over 10 years with 12 jobs. Residents have sued.1516 Bulloch County kept its moratorium and set up a citizen working group after a ban failed by one vote.17 Metter posted a study for a 100-megawatt project with $1.1 billion in real property and 40 jobs, though the city says no developer has approached it and no annexation request has been made.1825 The numbers explain the interest: large tax bases and few jobs. OpenAI's $20 billion campus in Effingham County shows how big the pull can get.19

Kroger broke ground on a 99,000-square-foot Marketplace on Veterans Memorial Parkway, anchoring a 21-acre center due in fall 2027.20 On Northside Drive, the old Publix and Kmart boxes are filled again with Academy Sports and HomeGoods.21 New space goes where the new rooftops are. Older corridors are being reused, not abandoned.
How we count: the pipeline includes filed, approved, and started projects in Bulloch and Candler counties. Plan figures count at their approved maximum. Project figures without a number here come from the list below, where each row carries its source. Bulloch and Candler counts come from Census estimates.
Current as of the verified dates shown
The larger projects, scaled to a market of about 98,000 people: 75 or more homes or apartments, commercial sites of 40,000 square feet or 10 corridor acres, industrial investment of $10 million or 50 jobs, public projects of $10 million or more, and 50 acres annexed or rezoned, plus smaller ones that change a corridor or an interchange. Smaller projects appear in the monthly issues.

Shaded areas are tinted by what each area is mostly adding. Dots are the projects in the list below: filled when construction has started, solid ring when approved, dashed when only filed. Roads and shapes are simplified. The counts below are every residential project in our pipeline data, assigned to the nearest area. A dash means nothing counted yet, not zero. Counts here are incomplete on purpose. They include projects approved since April 2025 that we could place on the map, plus earlier approvals that still shape their areas: the southeast corridor's planned townhomes and homes, and Brooklet's 300-acre Weyerhaeuser annexation. The southeast count is the city's own figure of about 1,342 units in the Burkhalter and Cawana corridor, including the Herman Rushing Road townhomes. The Hunnicutt subdivision is listed below but not yet placed, and the 714-acre Blue Fern plan is on hold and not counted.
| Growth area | Mostly adding | Homes and townhomes in the pipeline | Apartment units in the pipeline |
|---|---|---|---|
| US 301 South and I-16 | Hyundai suppliers, industrial sites | – | – |
| Old Register Road | Apartments, student cottages, homes | 448 | 725 |
| Downtown, campus and Northside | Student apartments, hotel, retail backfill | 0 | 108 |
| Southeast Statesboro | Homes, townhomes; a data center | 1,342 | 0 |
| Veterans Memorial Parkway west | Grocery-anchored retail, hotels | – | – |
| East Bulloch and Brooklet | Homes, a high school, aerospace jobs | 500 | 0 |
| Metter at I-16 | Auto suppliers; annexation at the exit | – | – |
| Downtown Metter | Little so far | – | – |
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| Old Register Road PUD expansion Old Register Rd and US 301 S, Statesboro | 237.59 acres; about 1,173 units planned: ~500 apartments, 225 student cottages, 202 townhomes, 246 homes; hotel, offices, retail | Approved VSB Development. Annexation of 99.53 acres and PUD expansion approved Aug 19, 2025. Unit counts are plan figures. | Aug 2025 | Statesboro PC packet, Aug 5, 2025 Grice Connect, Aug 19, 2025 | Oct 2, 2026 |
| Herman Rushing Road townhomes 285 Herman Rushing Rd, Statesboro | About 198 townhomes on 38.54 acres | Approved Blue Water Bulloch. Annexation and R-2 rezoning approved 4-1 May 20, 2025. | May 2025 | Statesboro Herald, May 2025 Statesboro PC packet, May 6, 2025 | Oct 2, 2026 |
| Hunnicutt subdivision US 80 East at Hagan Ln, Bulloch County | 134 lots on 51 acres | Approved County rezoning AG-5 to R-8 approved 3-2 | Aug 2025 | Grice Connect, Aug 5, 2025 | Oct 2, 2026 |
| Zetterower Road residential Zetterower Rd, Statesboro | 17.83 acres to R-4 (high density); 192 apartments (independent senior living and multifamily) | Filed Zack Smith Properties. Council tabled to Nov 17, 2026 for GDOT access. | Sep 2026 | Statesboro PC packet, Sept 1, 2026 Statesboro council agenda, Sept 15, 2026 Statesboro Brief, Sept 21, 2026 | Oct 2, 2026 |
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| Coca-Cola bottling plant redevelopment 401 S Main St, Statesboro | 7.54 acres; 108 apartments (240 beds); restaurant and brewery in the 1920 warehouse | Approved OZ Business. PUD rezoning and variance approved unanimously Aug 18, 2026. | Aug 2026 | Statesboro council minutes, Aug 18, 2026 Statesboro Brief, Aug 24, 2026 | Oct 2, 2026 |
| Georgia Southern Foundation hotel and conference center Tillman Rd between Fair Rd and S Main St, Statesboro | 13.5 acres; hotel, conference center, alumni condominiums | Approved Rezoned to mixed use June 16, 2026; developer and brand not announced | Jun 2026 | Statesboro council minutes, June 16, 2026 Statesboro Brief, May 18, 2026 | Oct 2, 2026 |
| Statesboro Summit rehabilitation Statesboro | 98 units; up to $12 million in bonds | Approved Housing authority bond issuance approved Sept 15, 2026 (rehab, not new units) | Sep 2026 | Statesboro Brief, Sept 21, 2026 | Oct 2, 2026 |
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| Kroger Marketplace Veterans Memorial Pkwy at Cypress Lake Rd, Statesboro | 99,000 SF store; $45.7 million; anchors a 21-acre center | Started Groundbreaking Aug 6, 2026; opening fall 2027. Rezoned to mixed use Dec 2, 2025, with a 20% residential requirement on the side facing Whispering Pines. | Aug 2026 | Statesboro council minutes, Dec 2, 2025 Statesboro council minutes, May 19, 2026 WTOC, Aug 6, 2026 | Oct 2, 2026 |
| Northside Drive store reuse Northside Dr E, Statesboro | Academy Sports (47,448 SF, former Publix); HomeGoods (former Kmart) | Started HomeGoods opened in the former Kmart. Academy Sports has sign variances (May 19, 2026) for the former Publix; construction start not confirmed. | May 2026 | Statesboro council minutes, May 19, 2026 Statesboro Brief, Feb 16, 2026 | Oct 2, 2026 |
| Fortner Road annexation Fortner Rd west of Crabby Ln, Metter | 46.76 acres; highway commercial zoning proposed for 990 Fortner Rd | Filed Annexation and rezoning hearing Sept 14, 2026; use not disclosed; outcome not yet confirmed | Sep 2026 | Metter public notice, Aug 12, 2026 Metter public notice, 990 Fortner Rd | Oct 2, 2026 |
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| Burkhalter Road data center 6539 Burkhalter Rd, Statesboro | 26.49 acres; ~230,000 SF; up to 99 MW requested; $1.2 billion over 10 years; 12 jobs | Approved 4AM Development. Rezoning approved 3-2 Aug 18, 2026. Special use permit not yet filed. Residents sued Sept 17. | Sep 2026 | Statesboro council minutes, Aug 18, 2026 Statesboro Brief, Aug 17, 2026 Statesboro Brief, Sept 28, 2026 | Oct 2, 2026 |
| Hyundai suppliers on US 301 South Bruce Yawn Commerce Park, Gateway park and nearby sites | Ajin/Joon Georgia $317M, 630 jobs; Ecoplastic $205M, 456 jobs; Hanon Systems $40M, 160 jobs | Started Ajin/Joon and Ecoplastic are operating; hired as of Aug 2026: Ajin/Joon 430, Ecoplastic 268. Hanon lists its Statesboro facility among its production sites; current employment is not published. Ecoplastic land request for worker housing tabled June 2026. | Aug 2026 | The Current, Sept 6, 2026 Statesboro Herald, June 2026 Hanon Systems, company network Gov. Kemp: Hanon, May 23, 2023 | Oct 2, 2026 |
| Gateway Regional Industrial Park Phase II Off US 301 S, Statesboro | 69-acre Cannady site; $1.52 million state grant to make it pad-ready | Approved OneGeorgia grant awarded June 2025 | Jun 2025 | Expansion Solutions, June 2025 | Oct 2, 2026 |
| revalyu recycling plant Gateway Regional Industrial Park, Statesboro | 43 acres; $200 million+; 121 jobs in two phases | Started Groundbreaking Oct 2023; phase one was due Q3 2025. Current operating status not confirmed. | Oct 2023 | Statesboro Herald, Oct 6, 2023 | Oct 2, 2026 |
| American Aero 16274 US 80 E, Brooklet | 45,000 SF; from 100+ to about 300 employees | Started Groundbreaking March 24, 2026; completion expected end of 2026 | Mar 2026 | Grice Connect, March 2026 | Oct 2, 2026 |
| Metter-Candler I-16 Industrial Park Lytell St, Metter | 130+ acres; DAS Corp. (300 jobs) and Doowon Climate Control ($30M+, 200 jobs) announced | Approved $103,500 state grant (Jan 2026) to renew certification and expand the park. DAS and Doowon were announced in 2023 and 2024; current operations and hiring not confirmed. | Jan 2026 | The Georgia Virtue, Jan 31, 2026 Georgia DED: DAS, Sept 2023 Gov. Kemp: Doowon, Feb 6, 2024 | Oct 2, 2026 |
| Project | Size | Status | Last change | Source | Verified |
|---|---|---|---|---|---|
| Southeast Bulloch High School Brooklet-Denmark Rd | Up to $165 million; $50.3 million in bonds sold | Approved Bonds sold Feb 2026; construction planned from summer 2026; opening about 2029-30. Start not confirmed. | Feb 2026 | WSAV, 2026 Statesboro Brief, Feb 16, 2026 | Oct 2, 2026 |
| Southeast corridor roads Burkhalter, Harville and Cawana roads, Statesboro | Planned: two roundabout projects ($3.3 million; $2.75 million) and Burkhalter widening ($2.8 million); $193,500 corridor study | Approved City-county cost-sharing agreement Feb 2026; county study contract Sept 1, 2026. The city counts about 1,342 units planned in the corridor. | Sep 2026 | Statesboro Brief, Feb 23, 2026 Statesboro Herald, June 2025 (units and road costs) Statesboro Brief, Aug 31, 2026 | Oct 2, 2026 |
This table is kept current between issues. Each issue keeps its own dated copy; corrections are noted on the issue.
Issues
First issue. A data center lawsuit in Statesboro and a data center study in Metter, the county's data center ban failing by one vote, a 46-acre annexation at Metter's I-16 exit, and the 18 projects shaping the area.
Sources: Statesboro City Council and Planning Commission; Bulloch County Board of Commissioners and Planning and Zoning Commission; Brooklet City Council; Metter City Council; the Development Authority of Bulloch County and the Candler County Industrial Authority; Bulloch County Schools and Georgia Southern University; state economic development announcements. Agendas and minutes are the primary record; press coverage fills in announcements and groundbreakings. We report what the record says and label what is not yet confirmed. Issues are dated and are not rewritten after they publish. Corrections are noted on the issue and carried into the next one.
See something we missed or got wrong? Tell us. How Redchip researches and verifies: Method.
Disclosure: the author is a partner in Vanguard Industrial Partners, which develops projects in the Southeast and may pursue projects in this market. General information only; see the disclaimer.